Back to blogCash flow & Construction

Why Profitable Construction Firms Still Run Out of Cash (and How to See It Coming)

5 min readKingsgrove Accounting4 November 2026
£120,000the job
£35,000profit
£21,250funded before you’re paid
In 30 seconds
Profit isn’t cash.In construction you pay out first and get paid last.
Four cash-eaters.Retentions, CIS, VAT and slow payers stretch the gap even further.
One simple fix.A 13-week cash forecast shows the hole weeks before you fall in it.
Skip to the fix
Full diary.Healthy profit.Empty bank by the 20th.
Sound familiar?

We hear it all the time from builders and contractors across Oxfordshire, Berkshire, Gloucestershire and Wiltshire. The jobs are going well. The accounts say you’re doing brilliantly. The bank balance says otherwise, and nobody can say where the money went.

Here’s where it goes.

The usual suspects

Five things quietly eating your cash.

1💰

Retentions: your money, their bank

Customers often hold back 3% to 5% of every payment until the job is finished, and some for a defects period that is frequently 12 months. It’s earned, but it isn’t in your account. Diarise every release date the day you sign.

2🏗️

Paying first, getting paid last

Wages go out every week. Suppliers want paying in 30 days or less. Your invoice goes out at month end on 30-day terms. One job can need weeks of funding before a penny comes back.

3🧾

CIS: tax taken before you see it

20% of a subcontractor’s labour is deducted at source. Sole traders get it back through their tax return. Limited companies can usually offset it against PAYE and National Insurance, or claim repayment after the year end. It comes back, just later. CIS guide

4🏛️

VAT: not your money

The VAT on your invoices is owed to HMRC, usually a month and seven days after each quarter ends. The domestic reverse charge has also changed the VAT pattern for many subcontractors since 2021. Close to the threshold? Read when to register for VAT.

5🐌

The slow payer

One late payer on a big invoice can wipe out a month’s cash flow. Chasing politely and hoping isn’t a plan. There’s a better way, and it’s further down this page.

Let’s put numbers on it

A great job that still breaks the bank.

Picture a £120,000 job over four months. Costs are £85,000, spread evenly. You invoice £30,000 at the end of each month, the customer pays 30 days later, and holds 5% retention. Made-up numbers, real pattern.

£35,000profit, a lovely 29% margin
£21,250funded before a penny comes in
£6,000retention still held after the last payment

Running cash balance, month by month

Below the line, the business is funding the job from its own pocket.
-£21,250
Month 1
-£14,000
Month 2
-£6,750
Month 3
£500
Month 4
£29,000
Month 5

Run two or three jobs like this at once and you can be profitable and out of cash in the same month.

See the numbers as a table
MonthCash outCash inRunning balance
1£21,250£0-£21,250
2£21,250£28,500-£14,000
3£21,250£28,500-£6,750
4£21,250£28,500£500
5£0£28,500£29,000
The fix

See it coming with a 13-week forecast.

It’s a simple week-by-week list of what you expect to come in and go out. Five steps, and you’re done.

1Start with today’s bank balanceThe real one, not the one in your head.
2List what’s due inEach invoice, on the day you realistically expect it to be paid. Be honest about the slow payers.
3List what must go outWages, subbies, suppliers, vehicles, insurance, loans, plus VAT, PAYE, CIS and corporation tax.
4Work out each week’s balanceAnywhere it dips below zero is a problem you now know about, with weeks to fix it.
5Update it weeklyMinutes once it’s set up, and the most useful number you’ll look at.
Quick wins

Six fixes you can do this week.

✍️Invoice sooner, and more oftenMove to stage or monthly applications, sent the day the work is done.
📝Agree terms before you start14 days beats 30, and written terms are far easier to enforce.
⏰Chase on day oneThe day after an invoice is due, not three weeks later.
⚖️Use late payment lawBusiness customers owe 8% over base rate plus £40, £70 or £100. Mentioning it often shakes an invoice loose.
🏦Set VAT and tax aside weeklyMove it to a separate savings account the moment you’re paid.
📅Diarise your retentionsPut every release date in your calendar and invoice for it on the day.
Quick answers

Common questions.

Short answers to the three things builders ask us most.

What is a 13-week cash flow forecast?

It is a week-by-week list of the money you expect to receive and the money you have to pay out over the next 13 weeks, with your running bank balance underneath. It shows you a shortfall weeks before it happens, while you can still do something about it.

Can I get my CIS deductions back sooner?

If you are a sole trader, CIS deductions are credited when you file your Self Assessment return. If you work through a limited company, the deductions can usually be set against your PAYE and National Insurance each month, or repaid after the tax year ends. Either way, the cash only comes back if your records are up to date.

What can I do if a customer pays late?

Business customers owe statutory interest of 8% above the Bank of England base rate on late commercial debts, plus a fixed sum of £40, £70 or £100 depending on the size of the debt. Most builders never claim it, but quoting it in a chaser often gets an invoice moving.

How we help

Want a hand building yours?

At Kingsgrove Accounting we work with construction and trade businesses who are growing and want to stay in control of their cash. We build your 13-week forecast with you, sort your CIS and VAT so you’re never surprised, and give you a monthly look at where the business is heading.

Let's talk

Ready to make the move?
It takes one call.

Every business is different. Book a free 30-minute call and we'll talk through your situation and work out exactly how we can help.